48-MONTH DEPLOYMENT WINDOW ACROSS STAGGERED AWARDS
| Period | Share of CAPEX | What it funds |
|---|---|---|
| Approvals Year 1 | 1% | LoA, FEED, permitting, equipment deposits |
| Construction Year 1 | 59% | Long-lead equipment, civils, MRF, contractor mobilization |
| Construction Year 2 | 40% | Balance of plant, mechanical completion, commissioning |
| Total per SPV | 100% | Concession years 1 – 3 (pre-commissioning) |
STAGGERED DEPLOYMENT (AWARD TO COD)
2026
2027
2028
2029
2030
2031
◄ COD
PD Pasarjaya
AP
C1 (59%)
C2 (40%)
◄ COD
Bandung
AP
C1 (59%)
C2 (40%)
◄ COD
Profile applied per SPV at its own CAPEX base. Source: locked anchor input · funding flow.